Floor flatness and the handling system
The Challenge
Racking, narrow-aisle trucks and automated systems can require different floor tolerances and load provisions. A late occupier specification can make a standard shell specification inadequate.
Our approach
The starting point is the floor performance actually bought. We compare that specification with the racking or automation requirements and the floor survey. If the occupier has changed the requirement, we assess the additional work; if the floor fails its original specification, that is a different commercial question. Keeping those two causes separate helps avoid paying for rectification as a variation.