Production equipment driving the building design
The Challenge
The machine order can change the building contract. Revised loads, pits or maintenance clearances may reach the site after the foundations have been priced or even poured.
Our approach
We compare the equipment vendor's requirements with the civil and services packages. Where they have changed, we identify the affected work and check what can still be omitted or altered without waste. The valuation needs to account for the whole revision, including foundations and connections, rather than accepting a separate extra from every trade without reconciling the interfaces.