Heat networks

Quantity surveying and claims support for heat network construction, energy centres and building connections.

Commercial challenges and how we approach them

Heat networks connect central plant to buildings through distribution pipework and associated equipment. The construction scope can cross streets, shared land and occupied premises, with excavation and reinstatement alongside plant installation. Energy-centre work, distribution routes and connections within buildings need identifiable package boundaries.

Street routes and building-entry changes

The Challenge

Moving a building entry can mean more than extra pipe: the trench, joints, chambers and reinstatement may all change.

Our approach

We compare the priced route with survey findings and instructed revisions. The valuation follows the affected civil, mechanical and reinstatement packages, including omissions and additional jointing or testing.

Energy centre, network and building boundaries

The Challenge

Different contractors may provide the energy centre, distribution network and heat interface units. Controls, flushing, power and connections can be excluded at the points where those packages meet.

Our approach

We review the package boundaries at each physical connection. The energy centre, network and building contractor need an agreed allocation for power, controls, flushing and commissioning attendance. Comparing those inclusions before award is more useful than discovering, when the connection is needed, that each contractor excluded it.

Phased connections and commissioning conditions

The Challenge

The first occupied buildings may need heat while later phases are still being built. That can require temporary heat and repeated flushing or balancing. It can also leave the commissioning team without the full load or connected systems assumed for the final tests.

Our approach

We establish the phased testing and temporary provisions bought, then assess additional attendance against actual connection readiness and the commissioning team's findings.

Retrofitting connections inside occupied buildings

The Challenge

Connecting existing buildings can involve restricted shutdowns, altered internal pipework and making good beyond the network trench. Access changes may create repeated visits across multiple properties.

Our approach

We distinguish the standard property connection from instructed internal alterations. Access appointments and visit records support any additional attendance, rather than adding the same allowance to every property.