Relevant Matter: definition and example

An event listed in the applicable JCT terms that may support your loss-and-expense entitlement, subject to conditions and amendments.

By Jack Butler-Kettle · Updated

Guidance for England and Wales. Check the contract, amendments and facts that apply to your job.

What it means in practice

Read this alongside SCL Delay and Disruption Protocol.

Relevant Matter is JCT terminology associated with loss-and-expense entitlement. The selected form and amendments determine the matters covered and the conditions for recovery. A Relevant Event and a Relevant Matter can overlap, but they serve different contractual purposes.

Check the money provision as well as the time provision. Delay and disruption recovery can help relate additional cost to the event and applicable terms.

Worked example

The facts

A specialist receives an extension of time after delayed access.

What happens

  1. It separately checks whether the cause falls within the applicable money-entitlement provisions.

  2. It records additional cost and explains why that event caused it.

What this shows

The extension is relevant background, not automatic proof that all associated costs are payable.

Sources

  1. Delay and Disruption Protocol, 2nd edition, February 2017. Society of Construction Law.