Variation pricing and compensation-event quotations
Price an instructed change to your package and record the basis for the additional time or money requested.
What is it?
We distinguish your original subcontract scope from changed work and use the procedure that applies to that subcontract. A valuation or quotation for one routine change, or an update to a defined batch of change-register entries. We use the procedure that applies to your contract, including NEC compensation events where relevant.
Additional events, revised scope, contested entitlement, specialist programme analysis and later negotiation are separately scoped.
How does it work?
You explain the work and the decision you need
You describe your trade package and the contractor who appointed you, the result you need and any urgent dates. The introductory conversation checks fit and availability; substantive assessment starts under an accepted instruction.
We agree the scope, responsibilities and fee
We check suitability, conflicts and capacity, then agree the scope, deliverables and timetable in writing, with a fixed fee or agreed hourly or daily basis. We explain payment terms, VAT and any separate costs before you accept. We identify the contract mechanism, event and stage being priced or assessed, including time-related inputs and the person responsible for notices. We confirm responsibility for urgent actions and specialist input.
You accept the scope and provide the information
You accept the written scope and provide the operative contract and amendments, original scope, instruction or event notice, changed information, quotation or cost records, quantities and relevant programme evidence. You identify missing items and the versions supplied; we agree who will obtain anything still needed.
We check the records and resolve gaps
We check the documents against the agreed scope, dates and versions, raise queries and record the basis on which work can proceed. Missing evidence stays identified; we agree any limited assessment or pause affected work until essential information is available. Live deadlines continue to run.
We establish the change and valuation basis
We compare the original and changed scope, check instruction authority and relevant notices, and identify the applicable valuation rules. We keep entitlement, cost and time questions distinct and refer specialist questions before relying on them.
We prepare the change calculation
We measure the change and prepare the calculation using the contractual basis, supported rates and records. We include omissions and credits and separate forecast costs from actual costs where the mechanism requires it.
We check time inputs and overlapping recovery
We coordinate any agreed programme input with the responsible planner, check overlaps with other changes and reconcile the calculation. For NEC work we check the actual form, options, dividing date and quotation procedure; a cost check does not itself determine an extension of time.
You approve the quotation for issue
You review the amount, assumptions and unresolved points. your package manager or authorised business owner authorises the relevant response or submission; formal instructions and assessments are issued only by the person with contractual authority.
We explain the result and complete the handover
We issue the checked change valuation or assessment and its current approval status, with notices and unresolved time or entitlement actions identified, explain the findings and record unresolved items, next actions, owners and dates. We answer the included clarification and correct our errors. New information, changed scope and later stages need a separate agreement; you decide whether to instruct them.
We confirm timing after checking the scope and available records. Flag any live deadline when you enquire; it continues to run while information is gathered.
What do you get?
You receive the outputs for the stages you choose. Each stage has its own scope, fee and endpoint; later stages are optional.
- A supported valuation or quotation with the applicable contractual basis, calculations and assumptions.
- An updated entry in the change register identifying agreement status, notices and next actions.
Each fixed piece of work includes one consolidated clarification round requested within 10 working days of issue, unless agreed otherwise. New records or scope need a separate agreement; we correct our own errors without charge.