Work and property inventory

Record the work, materials, plant and documents present at a defined handover or termination date.

by Jack Butler-Kettle · About 2 min readShare

How to use it

Inspect and photograph the position at the stated cutoff. Record ownership evidence and disagreements; possession alone does not establish title.

Work and property inventory

Inspect and photograph the position at the stated cutoff. Record ownership evidence and disagreements; possession alone does not establish title.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Work and property inventory

Scroll across if needed to read the whole record. A dash means no value has been entered.

Work and property inventory: completed fictional example
Reference / locationItem / work statusQuantityClaimed ownerEvidenceCondition / next action
INV-01 / Level 1Completed partition work120Work incorporated in projectDrawing mark-up M-14; photos P-1401Measure jointly; payment status separate
INV-02 / storeUnfixed board sheets40Westhaven Interiors, subject to contractInvoice I-18; delivery DN-18Dry and undamaged; title provision to check
INV-03 / Level 2Mobile tower T11Hire companyHire H-17Arrange agreed collection; retain receipt

Example cutoff: 14 October 2026 at 16:00. Preserve access records and avoid removing disputed property without resolving the relevant rights.

Understanding your results

Example cutoff: 14 October 2026 at 16:00. Preserve access records and avoid removing disputed property without resolving the relevant rights.

How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the related guidance for the context and checks behind this template.