Forecast final cost report

Combine recorded cost, unpaid commitments and uncommitted remaining work to forecast the final cost against budget.

by Jack Butler-Kettle · About 2 min readShare

How to use it

Remove overlap between actual cost, commitments and remaining estimates. Record the cutoff date and the source of each remaining-cost forecast.

Forecast final cost report

Remove overlap between actual cost, commitments and remaining estimates. Record the cutoff date and the source of each remaining-cost forecast.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Forecast final cost report

Scroll across if needed to read the whole record. A dash means no value has been entered.

Forecast final cost report: completed fictional example
Package / cutoffBudget (£)Cost to date (£)Unpaid commitments (£)Uncommitted remaining (£)Forecast final (£)Forecast over budget (£)Basis / action
Partitions / 30 Sep£100,000.00£60,000.00£25,000.00£20,000.00£105,000.00£5,000.00£5,000 forecast overrun; review remaining labour
Ceilings / 30 Sep£80,000.00£30,000.00£40,000.00£5,000.00£75,000.00-£5,000.00£5,000 below budget; scope and accruals checked

Positive variance means forecast over budget. Exclude already-recorded accruals from unpaid commitments to avoid counting them twice.

Understanding your results

Positive variance means forecast over budget. Exclude already-recorded accruals from unpaid commitments to avoid counting them twice.

How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.