Forecast final cost report
Combine recorded cost, unpaid commitments and uncommitted remaining work to forecast the final cost against budget.
by Jack Butler-Kettle · About 2 min readShare
How to use it
Remove overlap between actual cost, commitments and remaining estimates. Record the cutoff date and the source of each remaining-cost forecast.
Forecast final cost report
Remove overlap between actual cost, commitments and remaining estimates. Record the cutoff date and the source of each remaining-cost forecast.
Free blank template for your own project. The completed example is shown below. No email address required.
View the completed example
Completed fictional example
Westhaven refurbishment · 14 October 2026 · Version 1.0
Forecast final cost report
Scroll across if needed to read the whole record. A dash means no value has been entered.
| Package / cutoff | Budget (£) | Cost to date (£) | Unpaid commitments (£) | Uncommitted remaining (£) | Forecast final (£) | Forecast over budget (£) | Basis / action |
|---|---|---|---|---|---|---|---|
| Partitions / 30 Sep | £100,000.00 | £60,000.00 | £25,000.00 | £20,000.00 | £105,000.00 | £5,000.00 | £5,000 forecast overrun; review remaining labour |
| Ceilings / 30 Sep | £80,000.00 | £30,000.00 | £40,000.00 | £5,000.00 | £75,000.00 | -£5,000.00 | £5,000 below budget; scope and accruals checked |
Positive variance means forecast over budget. Exclude already-recorded accruals from unpaid commitments to avoid counting them twice.
Understanding your results
Positive variance means forecast over budget. Exclude already-recorded accruals from unpaid commitments to avoid counting them twice.
How it works
The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.
Read the related guidance for the context and checks behind this template.