What is the Scheme for Construction Contracts?

The Scheme is a set of default rules that steps in when your contract falls short of the Construction Act. Here is when it applies, and the dates and rules it sets.

by Jack Butler-Kettle · About 4 min readShare

The answer

The Scheme for Construction Contracts (England and Wales) Regulations 1998 is a set of default terms. It applies when a construction contract does not give the payment or adjudication rights that the Housing Grants, Construction and Regeneration Act 1996 requires.

Where that happens, the Scheme's terms apply in place of the missing ones. Part I covers adjudication and Part II covers payment. Scotland has its own Scheme, and Northern Ireland its own rules.

When the Scheme applies

You do not choose the Scheme. It applies by law, gap by gap.

If your contract has no adjudication clause, or one that falls short of the Act, the whole of Part I replaces it. If your contract leaves out a payment term the Act requires, the matching part of Part II fills that gap. The rest of your contract stays as it is.

Oral and part-written contracts can also fall within the Act. The missing or non-compliant terms determine which Scheme provisions apply. See understanding your agreement.

The payment dates it sets

Where Part II applies, it sets the valuation rules and payment dates.

Under paragraph 2, the sum due is the value of work done and materials supplied, together with other sums due and less amounts already paid.

An interim payment falls due 7 days after the payment period ends, or when you claim if later, under paragraph 4. The period is 28 days where the contract sets none. For the final-payment balance addressed by paragraph 5, the due date is 30 days after completion or the claim date, whichever is later. Other types of payment have their own provisions.

The final date for payment is 17 days after the due date under paragraph 8. The payer must send its payment notice within 5 days of the due date under paragraph 9. Its pay less notice must arrive at least 7 days before the final date for payment under paragraph 10.

So on a Scheme cycle, the payment notice is due by day 5 after the due date. Any pay less notice is due by day 10, and payment by day 17.

Your own dates come from your contract first. For a way to organise the documents and milestones, read your payment cycle and notices.

The adjudication rules it sets

Where Part I applies, it sets how an adjudication runs:

You begin by sending a notice of adjudication to every other party to the contract. The adjudicator is either the person named in the contract or someone chosen by a nominating body. Your referral notice, containing the full case, must reach the adjudicator within 7 days of the notice.

The adjudicator decides within 28 days of the referral, or 42 days if you agree, or longer if both sides agree. The adjudicator can also decide who pays the adjudicator’s fees.

Part I of the Scheme sets out each step. For how adjudication fits with the other ways to settle a dispute, see Construction disputes: your options.

Why the contract matters

Many contracts are amended to push the final date out or shorten your notice periods. The Scheme does not undo those changes if the contract still meets the Act. It steps in only where a required term is missing or does not work.

An unsigned contract can still contain agreed or incorporated payment terms. Establish the agreement first, then identify the particular gaps that the Scheme fills before putting dates in your diary.

Whether the Scheme applies to a term in your contract is a question of law on your documents. If a lot of money turns on it, ask your solicitor.

A Signed contract review and action plan can help turn the applicable payment provisions into a working record of obligations and dates.

Example

The facts

A subcontractor's order describes the work and price but appears to omit the final date for payment.

What happens

  1. The subcontractor gathers the full agreement, including terms referred to in the order and later agreed changes.

  2. They check whether the Construction Act applies and whether the payment provisions meet its requirements.

  3. If the relevant provision is missing or non-compliant, they identify the applicable Scheme provision and calculate the dates on that basis.

What this shows

The Scheme can fill a relevant gap. It is not a reason to replace every agreed payment term or use one timetable for every job.

Sources

  1. Scheme for Construction Contracts (England and Wales) Regulations 1998, SI 1998/649. legislation.gov.uk.
  2. Housing Grants, Construction and Regeneration Act 1996, Part II (Construction contracts), as amended by the Local Democracy, Economic Development and Construction Act 2009, Part 8. legislation.gov.uk.
  3. Scheme for Construction Contracts (England and Wales) Regulations 1998, SI 1998/649, Schedule, Part II, para 2 (Entitlement to and amount of stage payments). legislation.gov.uk.
  4. Scheme for Construction Contracts (England and Wales) Regulations 1998, SI 1998/649, Schedule, Part II, para 4 (Dates for payment). legislation.gov.uk.
  5. Scheme for Construction Contracts (England and Wales) Regulations 1998, SI 1998/649, Schedule, Part II, para 5 (Final payment balance). legislation.gov.uk.
  6. Scheme for Construction Contracts (England and Wales) Regulations 1998, SI 1998/649, Schedule, Part II, para 8 (Final date for payment). legislation.gov.uk.
  7. Scheme for Construction Contracts (England and Wales) Regulations 1998, SI 1998/649, Schedule, Part II, para 9 (Payment notice). legislation.gov.uk.
  8. Scheme for Construction Contracts (England and Wales) Regulations 1998, SI 1998/649, Schedule, Part II, para 10 (Notice of intention to pay less than the notified sum). legislation.gov.uk.
  9. Scheme for Construction Contracts (England and Wales) Regulations 1998, SI 1998/649, Schedule, Part I (Adjudication). legislation.gov.uk.