Activity schedule

In an NEC contract under Option A or C, the list of activities, each with a price, that makes up your price.

by Jack Butler-Kettle · About 2 min readShare

Further detail

Read this alongside the NEC Dictionary of Terms.

An activity schedule connects the price to identifiable parts of the work. It is not the same as the programme, which explains sequencing and timing. NEC Option A and Option C use the schedule differently, so do not assume the same payment assessment applies to both.

Check how activities are described and when they qualify for payment. Our Subcontract payment assessments service keeps the activity assessment and other adjustments traceable to the agreed mechanism.

Sources

  1. NEC Dictionary of Terms. NEC Contracts.

Activity schedule and rates examples

Use the pricing document required by your contract. Record completion criteria for activities and measurement rules for rate-based items.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Activity schedule

Scroll across if needed to read the whole record. A dash means no value has been entered.

Activity schedule: completed fictional example
ActivityCompletion criterionPrice (£)Position at cutoffEvidence
A-01 foundationsFoundations complete and inspection accepted£15,000.00CompleteF-01
A-02 envelopeRoof and external walls watertight£25,000.00IncompleteRoof detail outstanding

Schedule of rates

Scroll across if needed to read the whole record. A dash means no value has been entered.

Schedule of rates: completed fictional example
ItemDescriptionMeasured quantityUnitRate (£)Measured value (£)
R-01Partition finish80m²£25.00£2,000.00
R-02Special finish20m²£40.00£800.00

The examples illustrate pricing structures. They do not establish when an incomplete activity is payable or which quantities are contractually remeasurable.