Activity schedule

In an NEC contract under Option A or C, the list of activities, each with a price, that makes up your price.

by Jack Butler-Kettle · About 1 min readShare

Further detail

Read this alongside the NEC Dictionary of Terms.

An activity schedule connects the price to identifiable parts of the work. It is not the same as the programme, which explains sequencing and timing. NEC Option A and Option C use the schedule differently, so do not assume the same payment assessment applies to both.

Check how activities are described and when they qualify for payment. Our Subcontract payment assessments service keeps the activity assessment and other adjustments traceable to the agreed mechanism.