Skip to content

The delay damages in the contract I've been sent have no cap

If we finish late, the contract makes us liable for every loss the other party suffers, with no limit at all.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

What does this mean for me?

Contracts deal with late finishing in one of two ways. One is a fixed rate of damages for each day or week of delay. The other is a promise to pay whatever loss the other party suffers because of your delay. Either can come without a cap. On a large project, the other party's own delay damages, its site costs and other trades' claims can each exceed the value of your package.

With no cap, one late finish can cost you more than the whole contract is worth. It also makes the rest of the contract bite harder. A short delay notice period, or a right to deduct estimated losses from your payments, matters more with no limit on what can be taken.

Whether a particular damages clause is enforceable is a question for your solicitor. The commercial questions come first, and you answer them before you sign. What is the rate? What could it add up to on this programme? What cap should you ask for?

What do I need to do?

  1. Identify the rate or losses claimed, the counting rule, any limit and the extension-of-time provisions.
  2. Assess the financial exposure against a realistic overrun and your insurance position.
  3. Seek a defined rate, appropriate cap and workable time-relief provisions, with the proposed wording recorded.
  4. Decide whether the remaining exposure is acceptable before signing. Increasing the tender price may not make an uninsurable risk affordable.

To have this set up for you, see our Construction contract review before signing service.

Browse contracts and agreements in the Library

Browse the Library