Usually not: for most construction work, the law makes a pay-when-paid clause ineffective unless someone further up the chain is insolvent.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
The answer
A pay-when-paid clause makes your payment depend on the other party being paid by someone else, usually its client. Where your contract is a construction contract, section 113 of the Housing Grants, Construction and Regeneration Act 1996 makes that clause ineffective. The exception is where that someone, or a party further up the chain, is insolvent.
Since 2011, section 110 also treats a payment term as inadequate if it depends on obligations under another contract being met. The same applies if it depends on someone deciding they have been met, with limited exceptions. Where a clause fails, other payment terms take its place. But you still have to argue the point while your money is late.
Watch for clauses that are not labelled, too. Payment on receipt of the main contractor's certificate, or a set period after the client pays for your package, can do the same work. Whether the Act covers your contract, and what a particular clause does, is a question for your solicitor.
The commercial answer is simpler. Before you sign, ask for fixed payment dates instead. They cost the other party nothing to agree now, and cost you time and money to argue for afterwards.
To have clauses like this found and rated, and the replacement wording written before you sign, see our Construction contract review before signing service.