It must come from the right person on time, state the sum due and how it was worked out, and be served as your contract says.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
The answer
A pay less notice must come from the right person on time, state the sum due and how it was worked out, and be served as your contract says.
The sum is what the payer considers due on the date the notice is sent. That is the rule where section 111 of the Housing Grants, Construction and Regeneration Act 1996 applies. The heading does not decide it: the same tests apply whether it says pay less notice, payless notice or nothing at all.
So check who sent it and whether your contract lets them. Work out the final date for payment and the notice deadline using your contract's counting rules. Check the sum, the calculation behind it and how the notice reached you. A template can help you run these checks, but it cannot make a notice valid.
Keep the notice question separate from the argument about the valuation. Take advice where the effect of the notice, or whether the Act applies to your contract at all, is disputed.
To see what a valid notice should contain, see what a pay less notice should look like, line by line.