Vehicle movements during phased construction
The Challenge
A working depot still needs somewhere to move and park its fleet. Changing the construction phases can require temporary bays or routes that were never in the original price.
Our approach
We agree the operating layout used for pricing and record each area released for construction. If the sequence changes, we can assess the additional surfacing, barriers and repeated setup against that baseline. Permanent work and temporary arrangements remain separate, so the same bay is not effectively paid for twice.