Night working and daily airfield handback
The Challenge
Airfield work has to be handed back on time, even when access started late. Losing part of a night can leave too little time to complete the planned area and require another mobilisation.
Our approach
We compare the allowed working window with the actual release, setup, productive work and handback times. That detail helps explain whether another shift was caused by lost access, changed work or the contractor's own performance. Plant and shift records then provide a basis for assessing the additional cost.