Maintaining treatment through construction
The Challenge
Incoming wastewater does not stop while the works are upgraded. A changed construction sequence can keep bypasses or temporary treatment running for longer than priced.
Our approach
We establish the operating sequence used for tendering and record the actual release of tanks and process stages. Flow, plant and instruction records help explain extended temporary provision. Its cost is assessed against the package obligations, with ordinary operating attendance separated from the consequences of a changed construction arrangement.