Tank foundations and settlement allowances
The Challenge
Tank construction depends on the prepared foundation and the specified settlement criteria. Changed ground treatment or foundation levels can affect the tank contractor's start and fabrication sequence.
Our approach
We reconcile the foundation acceptance criteria with the tank contractor's required start condition. Surveys and technical instructions support the valuation of revised ground treatment or levels. Any claimed delay is assessed separately: additional concrete and waiting fabrication resources may share a cause, but neither proves the other.