Route access and crossing changes
The Challenge
Land access, road or river crossings and revised alignments can interrupt a continuous pipeline spread. A change may affect temporary roads, welding sequence and reinstatement as well as pipe length.
Our approach
We compare the planned route releases with the sections actually available to the pipeline spread. A blocked crossing can affect haul roads, welding and reinstatement as well as pipe length. The valuation separates the physical revision from evidenced extra mobilisation or temporary works, so the same interruption is not charged through several overlapping headings.