Brownfield tie-ins during a planned turnaround
The Challenge
Connections to an operating facility can depend on isolations and a tightly controlled shutdown. Unavailable workfronts or additional discovered scope can trigger standby, extra shifts and disputed recovery costs.
Our approach
We establish what work and access the turnaround price assumed. Extra discovered scope is measured separately from additional shifts or other recovery measures. For a claimed acceleration cost, the record should explain what was requested, which activities changed and which resources were added; working harder to complete an unchanged original obligation is a different position.