Remote infrastructure before mine construction
The Challenge
The mine construction team may need a road, camp, power and water before it can work effectively. Late enabling infrastructure can keep temporary provision running far beyond its allowance.
Our approach
We separate those enabling commitments from the permanent works and identify which package depends on each release. If temporary provision continues, the account records its actual use, duration and instruction. This makes the extension assessable without assuming that every camp or generator cost belongs to the delayed infrastructure contractor.