Long-lead plant and power availability
The Challenge
A completed data hall cannot be tested without power. Late transformers, switchgear or an energisation date can leave installation teams waiting and commissioning dates out of reach.
Our approach
We check the procurement dates against the construction programme, including who is responsible for making each connection available. If a date slips, the question is what it actually prevented: installation, individual equipment tests or integrated testing. That distinction matters when assessing standby, resequencing and prolongation. We use delivery records, programme updates and resource evidence to substantiate or challenge the costs, rather than treating every late delivery as a delay to completion.