Waste bunker and process-equipment interfaces
The Challenge
Waste reception, bunker structures, cranes, combustion equipment and boiler systems have closely connected dimensions and loads. Late equipment information can alter civil works that were committed much earlier.
Our approach
We compare the supplier's information dates and requirements with the civil package's assumptions. A revised load or opening can affect work already designed, ordered or cast. The valuation records those commitments as well as the new quantities, and checks whether superseded work can still be cancelled. This avoids treating a process-equipment revision as either a civil contractor's unexplained extra or a simple change to the equipment price.