Specification changes across repeated plots
The Challenge
A kitchen or façade revision may repeat across plots, but not every plot will be at the same stage. Some items are unordered, some can be cancelled, and others are installed. Applying one rate across the whole development can materially misstate the cost.
Our approach
We map the instruction to affected plots and procurement status. Repeated quantities, cancellations and abortive work are valued separately, with the remaining-phase forecast updated to match.