Suspension: definition and example
A temporary stopping of contractual performance under an applicable right, such as statutory suspension for qualifying non-payment after the required notice.
By Jack Butler-Kettle · Updated
Guidance for England and Wales. Check the contract, amendments and facts that apply to your job.
What it means in practice
Read this alongside section 112 of the Housing Grants, Construction and Regeneration Act 1996.
Statutory suspension for non-payment is a specific remedy with conditions, including a qualifying unpaid sum and notice of intention to suspend. It differs from termination and from simply abandoning the works. The applicable legislation and contract should be checked before any action is taken.
Obtain prompt advice on entitlement and service requirements. Late payment recovery can help organise the payment evidence without treating an enquiry as authority to stop work.
Worked example
The facts
A subcontractor considers stopping work after a payment deadline passes.
What happens
It verifies the amount payable and the documents governing that cycle.
It checks the statutory notice requirements and obtains advice before changing site attendance.
What this shows
An overdue payment prompts an assessment of the remedy; it does not make an immediate unnotified stoppage safe.