A rise claimed as one figure on the account is the easiest claim to refuse. Sort it by the route that could pay each part, and the part that is yours stops dragging down the part that is not.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
Why
Faced with one figure, the other party has an easy reply: the contract is fixed price, or the clause pays by its own method, not a percentage. Either answer kills the whole claim, including the parts you could have recovered. Most rises have several causes. The market part stays with you on a fixed price unless a clause moves it. Work the other party changed can be valued as a variation. And the extra cost of its delay pushing your purchases into dearer months can go into a loss and expense claim. Each part has its own route, its own evidence and its own method.
How do I do it?
- Read the contract for a fluctuations option or price adjustment clause, and note its base date, what it covers, its method and any notice condition.
- List each rise from the tender prices, the supplier increase notices and the invoices, with the date it took effect.
- Sort each rise by cause: market movement, work the other party changed, or work its delay pushed into later months.
- Value each part by its own route: the selected adjustment method for market rises and the contract's variation rules for changed work. For delay, establish a compensable cause, the affected purchase date, mitigation and the additional attributable cost.
- Check that no rise is counted under two routes, and state in the claim which part you accept as your own risk.
Our Contractual price increase recovery separates inflation, scope change and delay-related increases before testing the basis for recovery.