Defect and remedial cost schedule

Record alleged defects, the response, access arrangements and supported remedial costs item by item.

by Jack Butler-Kettle · About 2 min readShare

How to use it

Separate an allegation from an agreed defect. Record the opportunity to inspect and remedy, then support each cost with quantities and evidence.

Defect and remedial cost schedule

Separate an allegation from an agreed defect. Record the opportunity to inspect and remedy, then support each cost with quantities and evidence.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Defect and remedial cost schedule

Scroll across if needed to read the whole record. A dash means no value has been entered.

Defect and remedial cost schedule: completed fictional example
Item / locationAllegation / responseQuantityUnitRate (£)Proposed cost (£)Evidence / status
S-04 / corridorTwo missing label plates; accepted2each£15.00£30.00Photo P-1204; own team to fit 16 Oct
S-05 / Level 2Damaged board; responsibility disputed4m²£40.00£160.00Photo P-1210; request access and damage history

The £190 total is a proposed remedial estimate, not an agreed deduction. Preserve response and remedy records before concluding liability.

Understanding your results

The £190 total is a proposed remedial estimate, not an agreed deduction. Preserve response and remedy records before concluding liability.

How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the related guidance for the context and checks behind this template.