Construction cash-flow forecasting

Forecast the cash balance from dated receipts and payments, then test what happens when a receipt is delayed.

by Jack Butler-Kettle · About 2 min readShare

How to use it

Use bank cash and expected payment dates, not earned value. Carry each closing balance into the next opening balance and show any funding gap.

Construction cash-flow forecasting

Use bank cash and expected payment dates, not earned value. Carry each closing balance into the next opening balance and show any funding gap.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Construction cash-flow forecasting

Scroll across if needed to read the whole record. A dash means no value has been entered.

Construction cash-flow forecasting: completed fictional example
Period / scenarioOpening cash (£)Receipts (£)Payments (£)Closing cash (£)Timing / action
October baseline£20,000.00£60,000.00£70,000.00£10,000.00Includes £25,000 client receipt expected 16 Oct
October delayed receipt£20,000.00£35,000.00£70,000.00-£15,000.00£25,000 moves to November; arrange £15,000 funding or reschedule outflows
November after delay-£15,000.00£75,000.00£50,000.00£10,000.00Includes delayed £25,000; opening equals October delayed close

The first two rows are alternative scenarios, not consecutive periods. The November row follows the delayed scenario. Include VAT in cash flows where actually payable or recoverable.

Understanding your results

The first two rows are alternative scenarios, not consecutive periods. The November row follows the delayed scenario. Include VAT in cash flows where actually payable or recoverable.

How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the related guidance for the context and checks behind this template.