Skip to content

What does NEC4 ECC clause 60.1(8) mean?

A changed decision may support a compensation event under the actual contract.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

The answer

A changed decision can support a compensation event where the corresponding provision in your actual contract applies. ECC clause 60.1(8) concerns decisions communicated by its named roles; check the authority and wording governing your contract.

Identify two decisions, not merely a discussion followed by a first instruction. Preserve what was originally permitted or required, when it was communicated, what you reasonably did in reliance on it and the later authorised change. Check whether another event provision more specifically describes the change.

The assessment concerns the effect of the change: abortive work, altered procurement, additional work, savings and programme consequences. Separate work still required under the original Scope from additional work caused by the revised decision. Protect the actual notice deadline and avoid claiming the same effect under two event references.

Our Variations and compensation events preserves the original and revised decisions with their effects on work already planned or carried out. For a contested position: To have a refused event tested against the clause it falls under and pressed to implementation, see our NEC compensation event recovery service.

Browse changes and extra costs in the Library

Browse the Library