Skip to content

What does NEC4 ECC clause 60.1(2) mean?

Late access can support a compensation event where the contractual access obligation and relevant programme requirements are met.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 1 min readShare

The answer

Late access can support a compensation event where the actual contractual access obligation is unmet. The ECC clause 60.1(2) reference must be checked against your own contract wording and relevant programme requirements. A planned start date alone does not prove that the other party promised access on that date.

Keep the access provision, Contract Data, applicable Accepted Programme and evidence of when usable access became available. Identify the area and work affected; distinguish total exclusion from limited or conditional access. Record requests, refusals, handovers and any alternative workfaces offered.

Notify through the required route within the actual period. For the quotation, assess unavoidable resource effects and reasonable mitigation alongside any effect on planned Completion or Key Dates. Nineteen days without one workface is not automatically nineteen days' Completion delay or nineteen days of payable standing labour.

Our Variations and compensation events connects promised and actual access dates with the affected work and supporting records.

Browse changes and extra costs in the Library

Browse the Library