# Watch the notice regime on disputed variations

Payment notices and pay less notices can decide a disputed variation for the month, whatever its merits. Check every notice against the clock before you accept its number, because timing, sum, basis, sender and service all matter.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 9 October 2026 · About 2 min readShare

## Why

When a variation is undervalued, the argument goes to the merits: the hours, the rate, the instruction. But the payment cycle has its own rules, and they can decide the month whatever the merits. Identify the operative notified sum under the actual mechanism, which is not always the application amount. Check whether a notice properly states the sum considered due and the basis of calculation. It does that in its payment notice or, later, in a pay less notice under [section 111 of the Housing Grants, Construction and Regeneration Act 1996](<https://www.legislation.gov.uk/ukpga/1996/53/section/111n1>).

A defective payer notice may make the default-notice mechanism relevant. Check whether your application qualifies or a further notice is required, and whether a valid pay less notice reduces the sum. Keep the payment obligation separate from the underlying valuation dispute.

## How do I do it?

1.  Write down, for every application, its due date, the deadline for the payment notice and the last date for a pay less notice.
2.  Check each notice against those dates as soon as it arrives, before you read the figures.
3.  Check it names a sum, gives the basis for it, and comes from the person your contract says must send it.
4.  Take advice the same week if any of that is missing, before the final date for payment, not after the money is short.

Our [Variation Recovery](<https://www.quantsurv.com/claims/variation-recovery>) checks the notice history alongside the valuation evidence when a variation is disputed.

## Sources

1.  [Housing Grants, Construction and Regeneration Act 1996, s 111 (Requirement to pay notified sum)](<https://www.legislation.gov.uk/ukpga/1996/53/section/111n1>). legislation.gov.uk.