# Check revised drawings for potential variations

Compare each revision with the agreed contract baseline and log what changed. Check design responsibility, authority and notice requirements before treating additional work as a payable variation.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 9 October 2026 · About 2 min readShare

## Why

A revised drawing arrives with a new revision letter and a short note in the title block, and the site team builds it. Nobody calls it a variation, because nobody said the word. The added scope goes into the job as if it had always been there: a thicker slab, an extra cable run, a moved door. The cost goes in with it.

By the final account there are 30 revisions and no record of what each one changed. The argument becomes whether the tender drawings ever showed the work, and the other party answers by pointing at the current drawing. Checking on the day of issue is the only cheap moment to find the change.

## How do I do it?

1.  Log every drawing issue in a register with the date, the revision and who issued it.
2.  Compare each revision with the previous one on the day it arrives. Use the revision cloud where there is one, and a side-by-side check where there is not.
3.  Write a one-line note of what moved, and whether it adds, omits or changes the agreed contract scope, including accepted qualifications and design obligations.
4.  Write the same day if it does, identifying the potential change and seeking the required authorised instruction or confirmation, while protecting notice deadlines.

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) compares drawing revisions with the agreed scope and checks whether the contractual instruction process has been followed.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)