# Photograph the condition before you change it

Dated photographs can support evidence of the original condition, but do not alone decide entitlement or valuation. Before you open up, strip out or build over, photograph what is there.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## Why

Once the wall is opened, the ground dug or the old service stripped out, the original condition exists only in memory. Every argument about a change starts with what was there. Were the existing ducts where the drawings showed them? Was the ground as described? Was the finish already damaged?

Read photographs with their location, date, drawings and other records; check what they show and what remains uncertain. A dated photograph taken before the work costs a minute and needs no skill. Once the work is done, it cannot be taken at all, and the change is valued on the other party's account of what you found.

## How do I do it?

1.  Photograph what is there before any opening up, demolition, digging or building over: a wide shot first, then detail.
2.  Include something in the frame that fixes the location, such as a grid line, a door number or a drawing pinned to the wall.
3.  Leave the date and location settings on in the phone, and file the originals in the variation folder the same day.
4.  Write a short note wherever the condition differs from the drawings or the survey, and send it with the photographs.

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) preserves the original condition alongside the instruction and records of the changed work.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)