# Open a file per variation on the day it arises

A live file makes the instruction, valuation basis and cost evidence easier to check than scattered records assembled months later. Give each change one reference and one file: the instruction, the drawings it changes, the labour and plant it used, and the emails about it.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 7 October 2026 · About 2 min readShare

## Why

Evidence for a variation is created all over the job. The instruction sits in one inbox and the drawing in the document system. The labour is on allocation sheets, the plant on hire notes, and the emails are spread over 3 months. Left where it lands, the variation is just fragments that someone has to piece together when the account is argued.

That someone is usually not the person who was there, and by then the fragments have been moved, archived or deleted. A file opened on the day costs minutes, because each document goes in as it arrives. A file assembled at the final account may take longer and leave gaps that need corroborating evidence.

## How do I do it?

1.  Give every variation a reference number on the day it arises, and open a folder under that number.
2.  File the instruction, the confirmation, the drawings it changes and every email about it in the folder as they arrive.
3.  Add the weekly labour, plant and material records for the variation, taken from the allocation sheets.
4.  Keep a one-page summary at the front: what was instructed, when, by whom, and the running cost.

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) gives each change a traceable instruction, notice, valuation and evidence file. [Variation management setup](<https://www.quantsurv.com/claims#client-types>) is the separate setup-and-handover option for your own team.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)