# Argue changed conditions, not just changed quantities

Your contract rates were priced for set conditions, so a change done in harder conditions can justify a higher rate. Quantity times rate is only the start: say what changed and show why the rate should move.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 9 October 2026 · About 2 min readShare

## Why

A rate in your priced bills was built for a set of conditions: ground floor, clear access, summer, in sequence, in bulk. The other party then applies it to work on the fifth floor, in winter, in a live building. It calls that the contract rate. It is, but for different work.

An adjustment requires the relevant contractual valuation conditions to be met. Explain the changed conditions with diary and photographic evidence, then apply the permitted rate or valuation method. Quantity times rate is easy to check and easy to accept, which is why the other party proposes it. The adjustment is where the real cost of the change sits.

## How do I do it?

1.  Write down, for each variation, the conditions the contract rate assumed: location, access, sequence, season, quantity and working hours.
2.  Compare those with the conditions the changed work was actually done in, and list every difference.
3.  Price each difference separately, such as extra handling, lower output, standing time or out-of-hours premiums, with the record that shows it.
4.  Present an adjusted rate, new rate or other valuation only where the actual contract permits it, explaining the basis and avoiding overlap between adjustments.

Our [Variation Recovery](<https://www.quantsurv.com/claims/variation-recovery>) tests whether the original rates fit the changed work and supports any alternative valuation with records.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)