# I'm doing changed work on a say-so

Changes keep arriving by phone call and site conversation, and almost none of it is in writing.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

Work on verbal instructions is especially common on friendly jobs. A contracts manager asks for a wall to move, an engineer marks up a drawing, and your team gets on with it. Everyone agrees at the time. Months later, nobody can say who asked, what changed or when.

Your contract may need a written instruction, a confirmation sent a set way, or an instruction from a named person. A record of what was said and done proves those facts. It does not on its own make the change authorised or payable, or replace any notice your contract requires.

Leave it and the proof fades: messages get deleted, people move on and memories blur. A confirmation sent months later is not an automatic cure, so review the earlier directions now, while the evidence can still be found.

## What do I need to do?

1.  Record who gave the direction, their authority, the date, location and work affected.
2.  Confirm the direction through the contract's required communication route without assuming an informal message meets it.
3.  Keep the original scope and changed work together with the confirmation and any response.
4.  Record the resources and effects separately and follow the applicable valuation and notice procedure.

To have this done for you, see our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) and [Variation Recovery](<https://www.quantsurv.com/claims/variation-recovery>) services.