# I'm being told the change is included in my scope

We priced one thing, we are being made to build another, and the answer keeps coming back that it's all design development.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

A revised drawing adds work, and the other party calls it design development or says it was in your scope all along. The label on the drawing does not decide it. Start with the agreed contract scope: incorporated drawings and revisions, specification, accepted clarifications, document priority and design responsibility. Your tender is relevant evidence, but an unaccepted exclusion does not necessarily define that scope.

Build it without challenge and the extra goes into the job as if it was always there, with its cost. Some items will be clear changes, some will be included, and some will stay open. Whether a change is paid also depends on who instructed it, any notice your contract needs and how it is valued.

## What do I need to do?

1.  Compare the changed drawing or instruction with the agreed scope and accepted qualifications.
2.  Mark each item as included, changed or unresolved and identify the deciding document.
3.  Request written clarification and follow the applicable confirmation and notice requirements.
4.  Value supported changes under the contract's rules, keeping disputed scope and missing evidence visible.

To have this done for you, see our [Variation Recovery](<https://www.quantsurv.com/claims/variation-recovery>) and [Variation management setup](<https://www.quantsurv.com/claims#client-types>) services.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)