# The variation register is empty and the job is half built

What's been instructed, what's been priced, what's been agreed: nobody can say.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

Half the job is built and the variation register is empty, or it lives in one surveyor's head. Instructions are scattered across emails, meeting minutes and conversations. Some were confirmed the way the contract requires, most were not. Nobody can answer the three questions a variation account rests on: what was instructed, what was priced and what was agreed.

The cost comes every month, not just at the end. A change that is not on a list gets left out of an application, or assessed with no context. The longer the register stays empty, the more rebuilding it depends on other people's memories and goodwill. And a register is only an index of the evidence, not proof that any step happened.

## What do I need to do?

1.  Reconstruct changes from the original instructions, drawings, correspondence and site records.
2.  Give each item a fixed reference, date, scope description, evidence link, value and status.
3.  Mark missing authority or evidence explicitly and request the information needed to resolve it.
4.  Update the register as new changes arrive and reconcile it with applications, assessments and receipts.

To have this done for you, see our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) and [Variation Recovery](<https://www.quantsurv.com/claims/variation-recovery>) services.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)