# How are variations valued under a JCT contract?

By agreement, by an accepted quotation, or under the Valuation Rules, which start from your contract rates and move to fair rates or daywork.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## The answer

By agreement, by an accepted quotation, or under the Valuation Rules, which start from your contract rates and move to fair rates or daywork. The section number and rules depend on the actual JCT contract form, edition and amendments. The following is a common valuation approach to verify, not a universal clause sequence.

First, you and the other party can simply agree a price, before or after the work. Second, where the direction asked you to quote, your accepted quotation sets the price.

Otherwise the work is valued under the Valuation Rules, in the order and circumstances that your particular contract specifies. Work like the work you priced, done in similar conditions and quantities, is valued at your rates. Where the conditions or the quantity have changed significantly, your rates are the basis, with a fair allowance for the difference. Work unlike anything you priced is valued at fair rates and prices. Omitted work comes off at your rates. Daywork is used only where the work cannot properly be valued by measurement.

The rules also let other work be revalued if a variation substantially changes the conditions it is done in. Check which effects belong in the variation valuation and which use a separate loss-and-expense provision and notices. Prevent overlap instead of assuming every disruption cost follows the same route.

Check your amendments too, because they can change any of these rules. Then price each variation on the rule that fits it, and say which rule you used. When a valuation comes back on the wrong rule, answer it on the rule, not on the total. Our Variation Recovery service values each variation under the rules your contract sets and presses it to agreement.

For section 5 clause by clause, see [how JCT section 5 works](<https://www.quantsurv.com/variations/faq/jct-section-5-variations-and-valuation>).

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) measures the changed work and explains the rate or alternative build-up under the relevant JCT terms.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)