# Can I lose a variation claim by notifying it late?

Yes, under some contracts, so check the notice rules in yours as soon as a change comes up.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 1 min readShare

## The answer

Find out what triggers a notice, who must send it, to whom and how. Check whether a first notice must be followed by details, updates or a separate notice about time. Under some clauses, the timing affects whether you are paid at all; others work differently. What a late or incomplete notice does depends on the exact wording, any amendments and the evidence.

Keep the original message and proof that it was sent. A holding notice does not always replace the details that must follow. Notifying does not protect every cost and time point either. If a notice has gone in late or incomplete, take the wording to your solicitor.

To have the notice and confirmation periods your contract sets mapped and met on every change, see our [Variation management setup](<https://www.quantsurv.com/claims#client-types>) service.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)