# What is a provisional sum, and how is the work valued?

A provisional sum is an allowance for work not fully defined when the price is agreed. Its later instruction and valuation depend on the contract.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## The answer

A provisional sum is an allowance for work not fully defined when the price is agreed. Its later instruction and valuation depend on the contract.

It is not automatically a fixed price or an amount payable in full. Check what it covers, how it becomes authorised work and the applicable valuation procedure.

The [RICS New Rules of Measurement, NRM 2](<https://www.rics.org/content/dam/ricsglobal/documents/standards/NRM-2_Oct2022_Update.pdf>) distinguishes defined and undefined provisional sums in its measurement framework. Check whether those rules are incorporated and how the contract treats them.

A defined sum supplies specified information about the work; an undefined sum does not meet that information basis. Programme and preliminaries consequences require the actual rules and evidence.

A prime cost or PC allowance is different. In some building quotations it allows for a specified supply item, with installation and additions priced separately. Definitions vary between contracts and measurement systems.

For a homeowner choosing finishes, check the quantity, allowance per unit, permitted additions and whether installation is included. A £30/m² tile allowance cannot establish the finished floor price on its own.

When an allowance is replaced, remove the superseded amount and insert the properly assessed replacement. A £10,000 allowance replaced by £13,000 creates a £3,000 movement on the same basis.

Keep the instruction, measurement, quotation and agreed valuation together. Do not treat a low provisional sum as proof that the final cost will stay low.

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) reconciles the allowance with the instructed scope and its contractual valuation.

## Sources

1.  [NRM 2: Detailed measurement for building works, UK 2nd edition, October 2021 (reissued October 2022 as RICS practice information)](<https://www.rics.org/content/dam/ricsglobal/documents/standards/NRM-2_Oct2022_Update.pdf>). RICS.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)