# How is a variation valued in a construction contract?

By the valuation rules in your contract, which usually start from your contract rates and move on to adjusted rates, fair rates or daywork.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## The answer

So read those rules first. They may point to an existing rate, an adjusted rate, a new rate, a fair valuation, daywork or another method.

Then check whether the changed work, and the conditions it is done in, are like the work you priced. Work out the quantities, the resources and the preliminaries, your site running costs. Keep any separate question of time or disruption out of the valuation. What the work actually cost you is not a substitute for the method your contract sets.

Trace every figure to the instruction, the measurements, your records and your assumptions. Where the wording or the facts are uncertain, show the alternatives. A valuation sets out the evidence; it does not on its own make an unsupported rate payable.

### Keep the valuation basis with the item

Use the variation register to connect each claimed figure to the instruction and valuation records. State whether the amount uses an existing rate, an adjusted rate or another contractual basis.

Record quantities, units, assumptions and exclusions so another person can repeat the calculation. Compare the assessment with your own valuation at the same date, and explain the remaining difference.

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) supports the applicable rates, measurements and cost build-up for an ordinary change valuation.