# What if my variations are only disputed at the final account?

Rebuild each disputed variation from its instruction, valuation, payments and any agreements, item by item, before you decide how to respond.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 9 October 2026 · About 1 min readShare

## The answer

For each one, set out the scope and drawing revision, who authorised it and any notices. Add the measurements, the quote or assessment, the applications, certificates and payments, and what is still open.

Then check what your contract and the earlier documents say about certificates, agreements and reserved rights. Check too whether earlier figures are final or can still be corrected. An earlier assessment is evidence to test. It is not always a bar to reviewing the item again.

Keep the commercial reconciliation separate from any dispute procedure, and get the timeline in order before choosing a route. If finality or the right route is in doubt, that is a question for your solicitor.

To have each disputed variation rebuilt from its evidence and pressed to agreement, see our [Variation Recovery](<https://www.quantsurv.com/claims/variation-recovery>) service.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)