# Which daywork rates apply: RICS or CECA?

Use the daywork basis incorporated into your contract, including its edition, cost definitions, rates and agreed additions.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 3 min readShare

## The answer

Use the daywork basis incorporated into your contract, including its edition, cost definitions, rates and agreed additions. A RICS or CECA label alone does not settle the rate payable or whether daywork valuation is authorised for this work.

For building work, contracts may refer to a definition of prime cost of daywork and percentage additions in the priced documents. RICS's [Valuing change](<https://www.rics.org/content/dam/ricsglobal/documents/standards/valuing_change_1st_edition_rics.pdf>) describes that approach. Check the actual incorporated publication, trade and edition, what each cost component includes, and the contract's additions rather than treating a historical guidance document as a current tariff.

For civil engineering work, CECA publishes [Schedules of Dayworks Carried Out Incidental to Contract Work](<https://www.ceca.co.uk/product/ceca-schedules-of-dayworks-carried-out-incidental-to-contract-work-3rd-edition-11-august-2025>), with the third edition published on 11 August 2025. A newer publication does not automatically replace the edition or rates agreed in your contract.

Before submitting a sheet, establish the authorised work, valuation basis, labour/material/plant records and required verification. Apply only the agreed additions and reconcile costs already recovered elsewhere. If the contract leaves the basis unclear, seek a documented agreement rather than choosing a percentage or substituting the other party's rate.

## Key differences

Scroll across to read all columns.

Daywork bases compared
| Check | Building daywork basis | CECA daywork basis |
| --- | --- | --- |
| Source | The incorporated prime-cost definition and pricing documents | The incorporated CECA schedule and pricing documents |
| Rates and additions | Check permitted costs and the agreed percentage additions | Check the agreed edition, rates, inclusions and additions |
| Evidence | Authorised work, labour, plant, materials and required verification | Authorised work, labour, plant, materials and required verification |
| Which applies? | Only the basis agreed for the work; a RICS label is not a tariff | A newer schedule does not automatically replace the agreed basis |

## Example

### The facts

A groundworks subcontractor's daywork clause names the RICS definition for building work, with 110% on labour, 15% on materials and 10% on plant. The main contractor's valuation applies the contractor’s own 60% on labour.

### What happens

1.  One day's sheet shows prime costs of £400 for labour, £300 for materials and £250 for plant.
    
2.  With the subcontract percentages added, the day is worth £1,460: £840 of labour, £345 of materials and £275 of plant.
    
3.  At 60% on labour, the main contractor's figure for the same day is £1,260.
    
4.  The subcontractor answers with the daywork clause and the percentages they tendered.
    

### One day's daywork

| Item | Prime cost | With the percentage |
| --- | --- | --- |
| Labour, 110% | £400 | £840 |
| Materials, 15% | £300 | £345 |
| Plant, 10% | £250 | £275 |
| Total | £950 | £1,460 |

### What this shows

The day is agreed at £1,460. Across the 12 similar days on the sheets, that recovers £2,400 the lower labour percentage would have cut.

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) checks which schedule and additions the agreement incorporates before applying daywork rates.

## Sources

1.  [Valuing change](<https://www.rics.org/content/dam/ricsglobal/documents/standards/valuing_change_1st_edition_rics.pdf>). RICS.
2.  [Schedules of Dayworks Carried Out Incidental to Contract Work (third edition, 11 August 2025)](<https://www.ceca.co.uk/product/ceca-schedules-of-dayworks-carried-out-incidental-to-contract-work-3rd-edition-11-august-2025>). Civil Engineering Contractors Association.