# Set reminders ahead of the deadline, not on it

A reminder on the day an application or notice is due is a reminder to panic. Set one a few working days out so there's time to prepare the document properly, and a second on the day as a backstop.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 7 October 2026 · About 2 min readShare

## Why

An application due on Friday needs the measure done, the variations priced and evidenced, the document written and someone senior to sign it off. None of that happens in an hour. If the only reminder fires on the day, the application goes out thin, with figures nobody has checked. Or it goes out late and may not count for that cycle. The first reminder, a few working days out, turns the deadline into a task with a start date. The second, on the day, catches the cycle where the first was seen and forgotten. Between the two, the document gets the time it deserves.

## How do I do it?

1.  Set a preparation reminder early enough for the actual period; five working days may suit monthly applications but shorter notice periods need immediate action. Record any permitted submission window separately.
2.  Add a second reminder on the deadline day, addressed to the person who sends the document, as the backstop.
3.  Name the document in the reminder, with the cycle number, so nobody has to work out what it refers to.
4.  Start the document the day the first reminder fires, even if you only write the cover.

Our [Payment applications and valuations](<https://www.quantsurv.com/quantity-surveying#client-types>) assigns preparation dates, responsibility and escalation before a notice window closes.

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)

[Browse the Library](<https://www.quantsurv.com/library>)