# Put the call in writing straight after

Send a two-line email straight after the call: "As discussed, you've received the application and need nothing further", or "you've asked for X, which follows". The call helps you; the email records it.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 7 October 2026 · About 2 min readShare

## Why

A helpful call leaves nothing behind. The assessor tells you on the phone that everything has arrived and nothing more is needed. Then their payment notice cuts the application for lack of back-up. They will not remember what they said, and you cannot prove it. A two line email sent straight after the call puts what was said in writing for both sides. It also gives them the chance to correct it if you have misunderstood. If they say nothing, keep it as your contemporaneous account; silence does not necessarily mean agreement or acceptance. It is the cheapest evidence you will ever create, and it costs the goodwill of the call nothing.

## How do I do it?

1.  Email the person you spoke to within an hour of the call, summing up what was said in two or three lines.
2.  State plainly what they confirmed: the application was received, nothing further is needed, or what they asked for and when it follows.
3.  Copy the email to the same recipients the application went to.
4.  File the email in the cycle folder beside the note of the call.

Our [Payment applications and valuations](<https://www.quantsurv.com/quantity-surveying#client-types>) keeps the written follow-up with the application record so later questions can be traced.

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)

[Browse the Library](<https://www.quantsurv.com/library>)