# Photograph the work weekly before it is covered up

Take dated photographs as work progresses, with enough context to identify the area and task. They support valuation and progress records but do not establish entitlement on their own.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## Why

Much construction work is covered within weeks. Drainage is backfilled, insulation is boarded over, first fix is plastered in. When the assessor queries a quantity 3 months later, nobody can inspect the work. The argument becomes one person's word against another's. A dated photograph can materially support the measure or condition evidence, but should be read with the drawings and other records. The habit fails because photographs get taken when something goes wrong, not as a routine. So the one that matters is the one nobody took. A weekly walk with a phone, filed the same day, costs a few minutes. It builds a record of the whole job as it went up.

## How do I do it?

1.  Photograph work before concealment, even if that is before the weekly walk. Use the weekly check to find any remaining gaps.
2.  Check the phone's date and location stamping is on, so each image carries its own date.
3.  Photograph every element before it is covered, with something in shot that shows the location, such as a gridline or a door number.
4.  Upload the week's photographs the same day into a dated folder for the job, named by area.
5.  Reference the relevant folder in each application's back-up.

Our [Payment applications and valuations](<https://www.quantsurv.com/quantity-surveying#client-types>) includes an evidence routine for work that will become concealed before its value is agreed.

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)

[Browse the Library](<https://www.quantsurv.com/library>)