# Check the contract permits how you're sending it

If you serve by email, make sure the contract allows it. Keep the sent message, attachments and available delivery evidence. Read or delivery receipts may help, but may be unavailable and do not conclusively determine legal service.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 9 October 2026 · About 2 min readShare

## Why

Sending a document and serving it are different things, and the contract decides whether it was served. Say the contract requires post or hand delivery to a named address, and the application went by email. The payer can argue the cycle never started. Even where email is allowed, a dispute can turn on whether the application arrived. Then you have to prove it. Remembering that it went at about 4pm does not do that. Available server, delivery or read records can help alongside the complete message and the applicable service provisions.

## How do I do it?

1.  Read the notices clause and note which ways of serving documents it allows, and the address or portal for each.
2.  Send by an allowed method as well whenever email is not allowed, and keep the proof of posting or the signed delivery note.
3.  Request delivery or read receipts where available, without treating their absence or presence as conclusive proof of service.
4.  Save each receipt into the cycle folder beside the sent application on the day it comes back.
5.  Screenshot the portal's confirmation, with its timestamp, wherever the contract allows a portal, and file that too.

Our [Payment applications and valuations](<https://www.quantsurv.com/quantity-surveying#client-types>) tests the submission routine against the communication methods permitted by the contract.

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)

[Browse the Library](<https://www.quantsurv.com/library>)