# Get the paperwork looked at early

Whether a missing or late notice has fixed the sum in your favour is a question of documents and dates. The answer is often better than you expect, and the earlier the documents are checked, the more options are still open.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## Why

A missed or late notice may have fixed the sum in your favour under [section 110B of the Housing Grants, Construction and Regeneration Act 1996](<https://www.legislation.gov.uk/ukpga/1996/53/section/110B>). Whether it has turns on a few documents and dates: what was applied for, when it was served, what notice came back and when. Those facts are easiest to gather in the weeks after the cycle. The options that follow from them are all still open: a demand, a referral to adjudication or a negotiation from strength. Leave it 6 months and the receipts are lost and the people have moved. By then the payer has issued three more notices that muddy the position. An early check establishes the available position while the documents are easier to find; the time needed depends on the file.

## How do I do it?

1.  Gather the application as sent, the receipts, any notice received and the dates of each, the day a cycle looks wrong.
2.  Mark the dates and get the documents in front of someone who can check them that week.
3.  Write down what the check says about the position and what options remain open.
4.  Act on the option you choose while the dates are still fresh, rather than carrying the cycle into the final account.

Our [Underpayment recovery](<https://www.quantsurv.com/claims/underpayment-recovery>) starts with the actual application, notices and dates so the next step reflects the available evidence.

## Sources

1.  [Housing Grants, Construction and Regeneration Act 1996, s 110B (Payment notices: payee’s notice in default of payer’s notice)](<https://www.legislation.gov.uk/ukpga/1996/53/section/110B>). legislation.gov.uk.

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)

[Browse the Library](<https://www.quantsurv.com/library>)