# Follow the contract's format requirements to the letter

If the contract asks for a particular breakdown, form or reference, give it exactly that. "Substantially the same" is an argument you don't want to be having about your own money.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## Why

A contract that sets the form of an application hands the payer a checklist. A checklist is the easiest thing in the world to fail. Your own spreadsheet layout, a missing contract reference, a summary without their headings: each lets them say the application is not what the contract requires. In a good month nobody looks. Then comes the month the payer wants to avoid paying, or to escape a sum fixed by its own missed notice. The format point is the first place it goes, and the argument is about your money.

## How do I do it?

1.  Copy every requirement for the application's form, content, headings, reference and attachments from the contract onto a one page checklist.
2.  Build your application template around that checklist, so the required headings and references are there before any figures go in.
3.  Use the payer's own form if the contract requires it, with your own breakdown behind it, not instead of it.
4.  Run through the checklist on every application before it goes, and initial it.
5.  Keep the completed checklist in the cycle folder with the application.

Our [Payment applications and valuations](<https://www.quantsurv.com/quantity-surveying#client-types>) checks the application format and supporting information against the agreed requirements.

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)

[Browse the Library](<https://www.quantsurv.com/library>)