# Before relying on silence, confirm no notice was served

An empty inbox is not proof that no payment notice was given. Before treating your application as the sum due, check every agreed channel, including any portal, and ask the payer to confirm in writing.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 9 October 2026 · About 2 min readShare

## Why

With no payment notice and no pay less notice, your application can stand as the notified sum: the sum that must then be paid. That is worth acting on quickly. But the argument collapses if a notice turns up on a portal nobody checked. It also collapses if a notice went to an address the contract names and nobody reads. A demand for the full application, built on a silence that was not really silence, costs you credibility. You will need that credibility for the next cycle. Checking the channels first takes an hour. It turns an assumption into a fact you can rely on.

## How do I do it?

1.  Save your application as sent, with its calculation, attachments and the evidence of when and how it went.
2.  List every channel the contract allows for notices, including any portal and any named address, and check each one.
3.  Ask the payer in writing to confirm whether it gave a payment notice or pay less notice for the cycle, and when.
4.  Set the dates from the signed contract beside what you found: the due date, the notice windows and the final date for payment.
5.  Decide only then whether your application stands as the notified sum, and take advice where the route is unclear.

Our [Underpayment recovery](<https://www.quantsurv.com/claims/underpayment-recovery>) checks the delivery record and payment mechanism before relying on a missing notice.

If the whole notice window has passed without a word, see [what to do when no payment notice or pay less notice came](<https://www.quantsurv.com/underpaid/problems/no-notice-came>).

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)

[Browse the Library](<https://www.quantsurv.com/library>)